Specialized Expertise Includes Installation & Application Of:
Exterior Waterproofing Coating
Traffic Grade Coating
Structural Expansion Joint Systems
Concrete Repairs
Historic Repairs
Special Strengthening Systems

Current Projects

Exterior repair and refacing, replacement windows, exterior waterproofing, and more

Project Name: Florida Hospital, East Orlando
Owner: Adventist Health Systems
Project Location: Orlando, FL
Project Date: Current

Exterior repair and refacing of existing hospital patient tower. Removal of existing finish systems and the removal and replacement of existing windows. Installation of new impact resistant windows. Installation of new EIFS panels attached to the existing exterior wall system followed by the application of Dow Corning Allguard Exterior Waterproofing System.

Structural repair and waterproofing

Project Name: Fifth Third Plaza Structural Repair & Waterproofing
Property Manager: CB Richard Ellis, Orlando
Project Location: Lakeland, Florida
Project Date: Current

Removal and replacement of topping slab to over 20,000 SF of plaza deck surface followed by the removal of existing failed waterproof coating material. Installation of new topping slab and waterproof traffic system. Major concrete beam repairs including the installation of specialized carbon fiber strengthening system.

Concrete repairs, cleaning and painting of structural steel elements, crack sealing, and penetrating sealer

Project Name: JTA Skyway Guideway Repairs
Owner: Jacksonville Transportation Authority
Project Location: Jacksonville, FL
Project Date: Current

Various structural and remedial repairs to over 2.5 miles of elevated Skyway Guideway rail system. Repairs include concrete repairs, cleaning and painting or structural steel elements, crack sealing and the application of a penetrating sealer.

New waterproof traffic topping system, expansion joint replacement, replacement of sealants, and more

Project Name: Jacksonville Municipal Stadium
Owner: City of Jacksonville
Project Location: Jacksonville, FL
Project Date: Current

Removal of existing damaged and weathered deck coating materials followed by the installation of a new waterproof traffic topping system. Expansion joint removal and replacement, and the removal and replacement of sealants through out the stadium. Work requires the removal land reinstallation of seating and careful planning to accommodate
the facilities schedule.

 

Restocon